Updated by Dilip Dhakad about 2 years ago
- File Checklist for Online Training for Scheduler.docx Checklist for Online Training for Scheduler.docx added
Hi Team,
Hope you are doing well.
As discussed in today's meeting sharing you the proposed set of questions along with the word file as reference which needs to be added in the checklist.
Feel free to let me know if any further information required.
Updated by Rishabh Laad about 2 years ago
- Status changed from New to In Development
- Assignee changed from Mayur Rastogi to Mukul Jain
- Start date changed from 10/12/2022 to 10/18/2022
Updated by Mayur Rastogi about 2 years ago
Hi team
PFA the questions for Offline checklist.
Updated by Rishabh Laad about 2 years ago
- Status changed from In Development to In UAT Testing
Updated by Rishabh Laad about 2 years ago
Hi @Sourin Lodh , @Mayur Rastogi and @Dilip Dhakad , Kindly test this on dev.
Updated by Sourin Lodh about 2 years ago
Hi @Rishabh, me and Dilip did a test for online training. We are not able to view the comments in the excel export file.
And the below questions are not updated in the online checklist
8. Feedback Link Sent to Trainer & Participants?
Yes
No
NA
9. Did you collect the attendance?
Yes
No
NA
10. Did you collect and Upload Screenshots?
Yes
No
NA
Also keep Browse Option for Uploading Screenshots
=============
Questions for offline checklist are not uploaded and we are not able to add questions. If we click add question button, we get a "Hmmm… can't reach this page" error message
Updated by Sourin Lodh about 2 years ago
Updated by Renu Singh about 2 years ago
Team,
I tested the feature and see few questions are missing also comment section are also missing.
Thanks
Renu
Updated by Rishabh Laad about 2 years ago
Hi @RenuSingh and @Sourin Lodh , we are working on the changes suggested.
Updated by Mukul Jain about 2 years ago
Rishabh Laad wrote in #note-12:
Hi @RenuSingh and @Sourin Lodh , we are working on the changes suggested.
@RenuSingh @Sourin Lodh We have added screenshots and also comments are also added in reports along with the link of screenshots of images. On dev platform you can see settings on navigation bar. There is a configuration page there you can also go and add questions accordingly. If configuration is not visible just ping me once I'll provide the required permissions.
Updated by Sourin Lodh about 2 years ago
Hi @Rishabh I am not able to submit the checklist. Can you pls check once.
Updated by Sourin Lodh about 2 years ago
Hi Team,
I have completed one more round of UAT for the online checklist and its looks good from my end. I have also requested the Ops team to perform a UAT from their end.
For the offline checklist, I have added the checklist questions and submitted the checklist but the checklist is not reflected in checklist report tab.
Updated by Sourin Lodh about 2 years ago
- File clipboard-202211161134-5uqlg.png clipboard-202211161134-5uqlg.png added
- File Export (15).xlsx Export (15).xlsx added
Hi Team,
I did one more round of UAT for offline classes. The previous issue has been resolved. Checklist report file is not reflecting but the checklist is not capturing response for the below two questions:
Study Material, Lab & other necessary items (Like - Assessment, vouchers etc.) shared with the Trainer?
Study Material, Lab & other necessary items (Like - Assessment, vouchers etc.) shared with Participants?
Updated by Sourin Lodh about 2 years ago
- File Export (20).xlsx Export (20).xlsx added
Hi @Mukul Jain ,
Thank you for resolving the issue. Iteas is now capturing the above two questions in the export file for offline trainings.
have attached the output file for ref
Updated by Sourin Lodh about 2 years ago
Hi @Rishabh Laad Pls find attached the BRD for the enhancement req for checklist as confirmed by training ops.
Updated by Sourin Lodh about 2 years ago
- Status changed from In UAT Testing to In Development
Hi @Nisarg Desai @Mukul Jain @Rishabh Laad
Would you be able to add a date range field as well in the training checklist report tab so that we have the option to export a training checklist report for multiple days as well?
Thank you
Regards
Sourin
Updated by Rishabh Laad almost 2 years ago
- Status changed from In Development to In UAT Testing
Updated by Sourin Lodh almost 2 years ago
Updated by Rishabh Laad almost 2 years ago
- Status changed from In UAT Testing to Ready for Deployment
Updated by Rishabh Laad almost 2 years ago
- Status changed from Ready for Deployment to Deployed to Production