Feature #6151: Utilization Back end

Added by Rishabh Laad 3 months ago. Updated 2 months ago.

Status:
In UAT Testing
Priority:
Normal
Target version:
-
Start date:
12/02/2025
Due date:
12/08/2025 (about 3 months late)
% Done:

100%

Estimated time:
Priority Sequence:

Updated by Rishabh Laad 3 months ago Actions #1

  • % Done changed from 0 to 20

Updated by Rishabh Laad 3 months ago Actions #2

  • % Done changed from 20 to 40

Updated by Rishabh Laad 3 months ago Actions #3

  • % Done changed from 40 to 70

Updated by Rishabh Laad 2 months ago Actions #4

  • Status changed from In Development to In Testing
  • % Done changed from 70 to 100

Updated by Rishabh Laad 2 months ago Actions #5

  • Status changed from In Testing to In UAT Testing

Updated by Rishabh Laad 2 months ago Actions #6

  • Assignee changed from Esther Jelinal J to Rashmi Kulkarni